Defence Materiel (Question No. 2618)
David Johnston (WA, Liberal Party, Shadow Minister for Defence) Share this | Link to this | Hansard source
asked the Minister representing the Minister for Defence Materiel, upon notice, on 26 November 2012:
With reference to the major project Air Defence Target System JP 66 Phase 1, can the following details be provided:
(a) the date of the first date for first pass approval;
(b) the date of the first estimated date, time period, for second pass approval;
(c) the date of first pass approval;
(d) the date of second pass approval;
(e) the estimated acquisition cost when first proposed to Government;
(f) the current estimated acquisition cost;
(g) the date of estimated initial operational capability when first proposed to Government;
(h) the current date of estimated initial operational capability; and
(i) the reason(s) for the delay in this project, if applicable.
Bob Carr (NSW, Australian Labor Party, Minister for Foreign Affairs) Share this | Link to this | Hansard source
The Minister for Defence has provided the following answer to the honourable senator’s question:
The information you are seeking would require considerable research into historical Defence Capability Plans and project approval/management documents, and as such, is considered an unjustified diversion of resources.
Publicly available documents such as the Public Defence Capability Plan (http://www.defence.gov.au/publications/CapabilityPlan2012.pdf), Portfolio Budget Statements (http://www.defence.gov.au/budget/) and the Defence Annual Report (http://www.defence.gov.au/annualreports/) provide some detail on the information being sought.